Romania’s public road company CNAIR announced that the constructor commissioned two more sections of the Brasov-Bors motorway (Transilvania Motorway, officially A3), with a total length of 13.7 km, Wall-street.ro announced.
The two sections are Ogra-Iernut and Ungheni-Iernut, and they were commissioned on December 11-12, according to Romania-Insider.com.
The design and execution of the Ogra-Iernut section (3.6 km), part of the Ogra-Campia Turzii section, was made by Geiger Transilvania – part of Wilhelm Geiger group. The value of the contract was RON 55 million (EUR 11.8 mln). Work on this segment began in May 2016 and was scheduled for completion in September 2017.
The Ungheni – Ogra section, with a length of 10.1 km, was built by the association Strabag-Straco Grup, the value of the contract being RON 251.3 million (EUR 54 mln). Work began in June 2016 and was scheduled for completion in 12 months.